698
14 CFR Ch. I (1–1–24 Edition)
§ 151.43
and incidental costs, may be allowed
even though they were incurred before
that date, if they were incurred after
May 13, 1946; and
(4) Be supported by satisfactory evi-
dence.
[Doc. No. 1329, 27 FR 12351, Dec. 13, 1962, as
amended by Amdt. 151–8, 30 FR 8040, June 23,
1965; Amdt. 151–14, 31 FR 11747, Sept. 8, 1966]
§ 151.43 United States share of project
costs.
(a) The United States share of the al-
lowable costs of a project is stated in
the grant agreement for the project, to
be paid from appropriations made
under the Federal Airport Act.
(b) Except as provided in paragraphs
(c) and (d) of this section and in sub-
part C of this part, the United States
share of the costs of an approved
project for airport development (re-
gardless of its size or location) is 50
percent of the allowable costs of the
project.
(c) The U.S. share of the costs of an
approved project for airport develop-
ment in a State in which the unappro-
priated and unreserved public lands
and nontaxable Indian lands (indi-
vidual and tribal) is more than 5 per-
cent of its total land, is the percentage
set forth in the following table:
State
Percent
Alaska ......................................................................
62.50
Arizona .....................................................................
60.80
California ..................................................................
53.72
Colorado ..................................................................
52.98
Idaho ........................................................................
55.80
Montana ...................................................................
52.99
Nevada ....................................................................
62.50
New Mexico .............................................................
56.14
Oregon .....................................................................
55.64
South Dakota ...........................................................
52.53
Utah .........................................................................
60.65
Washington ..............................................................
51.53
Wyoming ..................................................................
56.33
(d) The United States share of the
costs of an approved project, rep-
resenting the costs of any of the fol-
lowing, is 75 percent:
(1) The costs of installing high inten-
sity runway edge lighting on a des-
ignated instrument landing runway or
other runway with an approved
straight-in approach procedure.
(2) The costs of installing in-runway
lighting (touchdown zone lighting sys-
tem, and centerline lighting system).
(3) The costs of installing runway dis-
tance markers.
(4) The costs of acquiring land, or a
suitable property interest in land or in
or over water, needed for installing op-
erating, and maintaining an ALS (as
described in § 151.13).
(5) The costs of any project in the
Virgin Islands.
[Doc. No. 1329, 27 FR 12351, Dec. 13, 1962, as
amended by Amdt. 151–17, 31 FR 16524, Dec.
28, 1966; Amdt. 151–20, 32 FR 17471; Dec. 6,
1967; Amdt. 151–35, 34 FR 13699, Aug. 27, 1969;
Amdt. 151–36, 34 FR 19501 Dec. 10, 1969]
§ 151.45 Performance of construction
work: General requirements.
(a) All construction work under a
project must be performed under con-
tract, except in a case where the Ad-
ministrator determines that the
project, or a part of it, can be more ef-
fectively and economically accom-
plished on a force account basis by the
sponsor or by another public agency
acting for or as agent of the sponsor.
(b) Each contract under a project
must meet the requirements of local
law.
(c) No sponsor may issue any change
order under any of its construction
contracts or enter into a supplemental
agreement unless three copies of that
order or agreement have been sent to
and approved by the Area Manager.
§§ 151.47 and 151.49 apply to supple-
mental agreements as well as to origi-
nal contracts.
(d) This section and §§ 151.47 through
151.49 do not apply to contracts with
the owners of airport hazards, (as de-
scribed in § 151.39(b)), buildings, pipe
lines, power lines, or other structures
or facilities, for installing, extending,
changing, removing, or relocating that
structure or facility. However, the
sponsor must obtain the approval of
the Area Manager before entering into
such a contract.
(e) No sponsor may allow a con-
tractor or subcontractor to begin work
under a project until—
(1) The sponsor has furnished three
conformed copies of the contract to the
Area Manager; and
(2) The Area Manager agrees to the
issuance of a notice to proceed with the
work to the contractor. However, the
Area Manager does not agree to the
699
Federal Aviation Administration, DOT
§ 151.47
issuance of such a notice unless he is
satisfied that adequate replacement
housing is available and has been of-
fered to affected persons, as required
for project eligibility by § 151.39(a)(5).
(f) Except when the Area Manager de-
termines that the sponsor has pre-
viously demonstrated satisfactory en-
gineering and construction supervision
and inspection, no sponsor may allow a
contractor or subcontractor to begin
work, nor may the sponsor begin force
account work, until the sponsor has
notified the Area Manager in writing
that engineering and construction su-
pervision and inspection have been ar-
ranged to insure that construction will
conform to FAA approved plans and
specifications, and that the sponsor has
caused a review to be made of the
qualifications of personnel who will be
performing such supervision and in-
spection and is satisfied that they are
qualified to do so.
[Doc. No. 1329, 27 FR 12351, Dec. 13, 1962, as
amended by Amdt. 151–31, 34 FR 4885, Mar. 6,
1969; Amdt. 151–39, 35 FR 5537, Apr. 3, 1970]
§ 151.47 Performance of construction
work: Letting of contracts.
(a)
Advertising required; exceptions.
Unless the Administrator approves an-
other method for use on a particular
airport development project, each con-
tract for construction work on a
project in the amount of more than
$2,000 must be awarded on the basis of
public advertising and open competi-
tive bidding under the local law appli-
cable to the letting of public contracts.
Any oral or written agreement or un-
derstanding between a sponsor and an-
other public agency that is not a spon-
sor of the project, under which that
public agency undertakes construction
work for or as agent of the sponsor, is
not considered to be a construction
contract for the purposes of this sec-
tion, or §§ 151.45, 151.49, and 151.51.
(b)
Advertisement; conditions and con-
tents.
There may be no advertisement
for bids on, or negotiation of, a con-
struction contract until the Adminis-
trator has approved the plans and spec-
ifications. The advertisement shall in-
form the bidders of the contract and re-
porting provisions required by § 151.54.
Unless the estimated contract price or
construction cost is $2,000 or less, there
may be no advertisement for bids or
negotiation until the Administrator
has given the sponsor a copy of a deci-
sion of the Secretary of Labor estab-
lishing the minimum wage rates for
skilled and unskilled labor under the
proposed contract. In each case, a copy
of the wage determination decision
must be set forth in the initial invita-
tion for bids or proposed contract or in-
corporated therein by reference to a
copy set forth in the advertised or ne-
gotiated specifications.
(c)
Procedure for the Secretary of La-
bor’s wage determinations.
At least 60
days before the intended date of adver-
tising or negotiating under paragraph
(b) of this section, the sponsor shall
send to the Area Manager, completed
Department of Labor Form DB–11, with
only the classifications needed in the
performance of the work checked. Gen-
eral entries (such as ‘‘entire schedule’’
or ‘‘all applicable classifications’’) may
not be used. Additional necessary clas-
sifications not on the form may be
typed in the blank spaces or on an at-
tached separate list. A classification
that can be fitted into classifications
on the form, or a classification that is
not generally recognized in the area or
in the industry, may not be used. Ex-
cept in areas where the wage patterns
are clearly established, the Form must
be accompanied by any available perti-
nent wage payment or locally pre-
vailing fringe benefit information.
(d)
Use and effectiveness of the Sec-
retary of Labor’s wage determinations.
(1)
Wage determinations are effective only
for 120 days from the date of the deter-
minations. If it appears that a deter-
mination may expire between bid open-
ing and award, the sponsor shall so ad-
vise the FAA as soon as possible. If he
wishes a new request for wage deter-
mination to be made and if any perti-
nent circumstances have changed, he
shall submit a new Form DB–11 and ac-
companying information. If he claims
that the determination expires before
award and after bid opening due to un-
avoidable circumstances, he shall sub-
mit proof of the facts which he claims
support a finding to that effect.
(2) The Secretary of Labor may mod-
ify any wage determination before the
award of the contract or contracts for
which it was sought. If the proposed