Volume: 1Date: 2024-01-01Original Date: 2024-01-01Title: Section 17.31 - Dismissal or summary decision of contract disputes.Context: Title 14 - Aeronautics and Space. CHAPTER I - FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION. SUBCHAPTER B - PROCEDURAL RULES. PART 17 - PROCEDURES FOR PROTESTS AND CONTRACT DISPUTES. Subpart C - Contract Disputes.
§ 17.31 Dismissal or summary decision of contract disputes. (a) Any party may request by motion, or the ODRA on its own initiative may recommend or direct, that a contract dispute be dismissed, or that a count or portion thereof be stricken, if: (1) It was not timely filed; (2) It was filed by a subcontractor or other person or entity lacking standing; (3) It fails to state a matter upon which relief may be had; or (4) It involves a matter not subject to the jurisdiction of the ODRA.
Code of Federal Regulations / Title 14 - Aeronautics and Space / Vol. 1 / 2024-01-01124
(b) Any party may request by motion, or the ODRA on its own initiative may recommend or direct, that a summary decision be issued with respect to a contract dispute, or any count or portion thereof if there are no material facts in dispute and a party is entitled to a summary decision as a matter of law. (c) In connection with any potential dismissal of a contract dispute, or summary decision, the ODRA will consider any material facts in dispute in a light most favorable to the party against whom the dismissal or summary decision would be entered, and draw all factual inferences in favor of that party. (d) At any time, whether pursuant to a motion or on its own initiative and at its discretion, the ODRA may: (1) Dismiss or strike a count or portion of a contract dispute or enter a partial summary decision; (2) Recommend to the Administrator that the entire contract dispute be dismissed or that a summary decision be entered; or (3) With a delegation from the Administrator, dismiss the entire contract dispute or enter a summary decision with respect to the entire contract dispute. (e) An order of dismissal of the entire contract dispute or summary decision with respect to the entire contract dispute, issued either by the Administrator or by the ODRA, on the grounds set forth in this section, shall constitute a final agency order. An ODRA order dismissing or striking a count or portion of a contract dispute or entering a partial summary judgment shall not constitute a final agency order, unless and until such ODRA order is incorporated or otherwise adopted in a final agency decision of the Administrator or the Administrator's delegee regarding the remainder of the dispute. (f) Prior to recommending or entering either a dismissal or a summary decision, either in whole or in part, the ODRA shall afford all parties against whom the dismissal or summary decision would be entered the opportunity to respond to a proposed dismissal or summary decision.